Saturday, June 13, 2015 - 16:04

Our second PDU to be connected today - PDU 303A - was brought down at 4:03 PM.

The next update will occur when PDU 303A has been successfully tested, and we are ready to move on to PDU number 3 - PDU 105A

This update should be posted in approximately 30 minutes.

Saturday, June 13, 2015 - 15:59

PDU 202A has been successfully tested!

We are about to start bringing down PDU 303A.    We have made up 10 minutes on our schedule.

The next update will occur when PDU 303A is actually brought DOWN.

 

Saturday, June 13, 2015 - 15:46

The first PDU - 202A - was successfully brought down at 3:25 AM.  

Right now, we are approximately 25 minutes behind schedule, but we are not willing to "rush into failure," as one of our esteemed colleagues always says.  We are making sure that everything being done is being done correctly so it doesn't have to be done again.

The next posting will occur when PDU 202A has been successfully brought back up, and we are ready to take down the second PDU of the day - PDU 303A.

 

 

Saturday, June 13, 2015 - 15:08

We are about to begin this afternoon's EPO Swich activities -  PDU 202A is starting at 3:03 PM.

I will provide another update on AZCOOP and on the Meet Me Bridge Line at (602) 771-9093 when PDU 202A has been successfully connected, and we are about to move to PDU 303A.   This update should occur within the next 30 minutes.

Saturday, June 13, 2015 - 14:37

The completion of the Emergency Power Off (EPO) Switch activities, which entails the connection of the remaining five (5) Power Distribution Units (PDUs) to the EPO switch is a GO, and will be starting with PDU 202A at precisely 3:00 PM.

At the present time, the Meet Me Bridge Line was established at 602-771-9093 at 2:36 PM, and will be available through the entire effort.   We are still awaiting the qarrival of some of the personnel that will be executing this activity, but we are confident in our previously announced start time of 3:00 PM.

Additional updates will occur through AZCOOP as we move to each PDU through the entire effort.

The next update will be to announce the commencement of this activity with PDU 202A at 3:00 PM

 

Friday, June 12, 2015 - 10:32

The Emergency Power Off switch connections to the remaining five (5) Power Distribution Units have been rescheduled for Saturday, June 13, 2015, beginning at 3:00 PM.

The Schedule is as follows:    

PDU 202A    Group 1   -   3:00 PM

PDU 303A    Group 2   -   3:45 PM

PDU 105A   Group 3   -    4:30 PM

PDU 202B   Group 1   -    5:00 PM

PDU 303B   Group 2   -    5:30 PM

Group 1 Impacted Customers  -  DOR, DOE, Gov. Ofc., Dept. of Gaming, Dept. of Racing, ROC, AZ Children's, AZNet I and II, SACNET, Gila County, DOC, ASET SPR

Group 2 Impacted Customers  -  ASET Mainframe, SPR, DES, SSA, DSG

Group 3 Impacted Customers  -  ASET Operations

A Bridge Line will be available as of 3:00 PM -   Please dial into 602-771-9093.

The next communication that will be posted on AZCoop will be made for the start of these EPO Switch connection activities at 3:00 PM tomorrow afternoon. 

Saturday, June 6, 2015 - 07:21

All activity related to the EPO Project for Saturday 06/06/2015 has been cancelled. The FIKE Subject Matter Expert (SME) had a family emergency and was unable to be on-site to certify the fire panel. As a result all EPO activity has cancelled.

A notification regarding the rescheduling of this activity will be forthcoming.

Thank you.

Saturday, May 23, 2015 - 05:38

All work related to the installation of the Temporary ATS has been completed successfully.. All CRAC units are up and running w/o issue.

The Customer Bridge Line was terminated at 0535. If you have any questions please call the State Data Center at 602-364-4444 option 2.

Thank you.

Saturday, May 23, 2015 - 05:16

Installation of the Temporary ATS was completed successfully.. All CRAC units have been returned to Data Center power and are up and running. Crews are continuing to perform minor clean-up work. Current ETA for completion of all clean-up work is 06:00 AM.

A customer Bridge Line has been established at 866-789-8818, Passcode 574769#. The Bridge Line will be left up until 05:30 AM for any questions.

Thank you for cooperation and patience.

Saturday, May 23, 2015 - 03:41

Cutover to the temporary ATS is complete. Testing of ATS has been successfully completed. The process of disconnecting the 2nd and 3rd floor CRAC units from the backup generator and reconnecting to the SDC panels has begun.

Current ETA for completion of all work is 06:00 AM.

A customer Bridge Line has been established at 866-789-8818, Passcode 574769#.

Next update will be performed at 04:15 AM.

Saturday, May 23, 2015 - 03:04

Installation of the temporary ATS unit for the 2nd & 3rd floor equipment rooms started at 1030 PM. Tie in to the temporary ATS is complete. The ATS has been energized and the Russell Gear has been successfully tested. Additional testing is in progress. Once these test are complete the process of disconnecting the 2nd and 3rd floor CRAC units from the backup generator will begin.

Current ETA for completion of all work is 06:00 AM.

A customer Bridge Line has been established at 866-789-8818, Passcode 574769#.

Next update will be performed at 03:30 AM.

Saturday, May 23, 2015 - 03:03

Installation of the temporary ATS unit for the 2nd & 3rd floor equipment rooms started at 1030 PM. Tie in to the temporary ATS is complete. The ATS has been energized and the Russell Gear has been successfully tested. Additional testing is in progress. Once these test are complete the process of disconnecting the 2nd and 3rd floor CRAC units will begin.

Current ETA for completion of all work is 06:00 AM.

A customer Bridge Line has been established at 866-789-8818, Passcode 574769#.

Next update will be performed at 03:30 AM.

Saturday, May 23, 2015 - 02:29

Installation of the temporary ATS unit for the 2nd & 3rd floor equipment rooms started at 1030 PM. Cutover to temporary ATS in progress. Currently we do not have an ETA on the completion of work.

A customer Bridge Line has been established at 866-789-8818, Passcode 574769#.

Next update will be performed at 0300 AM.

Saturday, May 23, 2015 - 01:58

Installation of the temporary ATS unit for the 2nd & 3rd floor equipment rooms started at 1030 PM. Cutover to temporary ATS in progress. Currently we do not have an ETA on the completion of work.

A customer Bridge Line has been established at 866-789-8818, Passcode 574769#.

Next update will be performed at 0230 AM.

Saturday, May 23, 2015 - 01:37

Installation of the temporary ATS unit for the 2nd & 3rd floor equipment rooms started at 1030 PM. Cutover to temporary ATS in progress. Currently we do not have an ETA on the completion of work.

A customer Bridge Line has been established at 866-789-8818, Passcode 574769#.

Next update will be performed at 0200 AM.

Saturday, May 23, 2015 - 01:09

Installation of the temporary ATS unit for the 2nd & 3rd floor equipment rooms started at 1030 PM. The switch of the 2nd & 3rd floor CRAC units to the backup generators has been completed. The process of connecting to the temporary ATS will begin at 01:30 AM. Currently we do not have an ETA on the completion of work.

A customer Bridge Line has been established at 866-789-8818, Passcode 574769#.

Next update will be performed at 01:30 AM.

Saturday, May 23, 2015 - 00:29

Installation of the temporary ATS unit for the 2nd & 3rd floor equipment rooms started at 1030 PM. The work of switching the CRAC units on the 3rd floor to the backup generators is completed. The switch of the 2nd floor CRAC units is currently underway and progressing as expected. Currently we do not have an ETA on the completion of work.

A customer Bridge Line has been established at 866-789-8818, Passcode 574769#.

Next update will be performed at 01:00 AM.

Thank you.

Saturday, May 23, 2015 - 00:00

Installation of the temporary ATS unit for the 2nd & 3rd floor equipment rooms started at 1030 PM. The work of switching the CRAC units on the 3rd floor to the backup generators is completed. The switch of the 2nd floor CRAC units is currently underway and progressing as expected. Currently we do not have an ETA on the completion of work.

A customer Bridge Line has been established at 866-789-8818, Passcode 574769#.

Next update will be performed at 12:30 AM.

Thank you.

Friday, May 22, 2015 - 23:29

Installation of the temporary ATS unit for the 2nd & 3rd floor equipment rooms started at 1030 PM. The work of switching the CRAC units to the backup generators is currently underway and progressing as expected.

A customer Bridge Line has been established at 866-789-8818, Passcode 574769#.

Next update will be performed at 12:00 AM..

Thank you.

Friday, May 22, 2015 - 23:02

Installation of the temporary ATS unit for the 2nd & 3rd floor equipment rooms started at 1030 PM. The work of switching the CRAC units to the backup generators is currently underway and progressing as expected.

A customer Bridge Line has been established at 866-789-8818, Passcode 574769#.

Next update will be performed at 11:30 PM.

Thank you.