Temporary ATS Installation

Installation of the Temporary ATS was completed successfully.. All CRAC units have been returned to Data Center power and are up and running. Crews are continuing to perform minor clean-up work. Current ETA for completion of all clean-up work is 06:00 AM.

A customer Bridge Line has been established at 866-789-8818, Passcode 574769#. The Bridge Line will be left up until 05:30 AM for any questions.

Thank you for cooperation and patience.