ATS Installation at the SDC - Update

As of 7:03 AM, all CRAC Units on Panels 2-1 and 2-2 have been successfully connected to the new permanent ATS.

Corbins Electric is now working on shutting down the final CRAC Unit, CRAC 208.   Once this CRAC Unit is connected to the new permanent ATS, this project will be completed. 

We are now approximately one hour ahead of schedule, with no issues encountered. 

There is still a Meet-Me Bridge Line established at 602-771-9093.

The next update will be posted at 8:00 AM.

 

 