ATS Installation at the SDC - Update

As of 6:01 AM, all CRAC Units on Panel A-1 have been successfully connected to the new permanent ATS.

Also, all CRAC Units on Panel 2-1 have been successfully shut down and are now in process of being connected to the new permanent ATS.

We continue to be about 45 minutes ahead of schedule at the present time, and there have been no issues encountered.

There is a Meet Me Bridge Line available at 602-771-9093. 

The next update will be posted at 7:00 AM.