Automatic Transfer Switch Install Pre-Work in the State Data Center

Good morning,

Beginning at 3:00 AM, we wil begin activities to prepare for the installation of a new Automatic Transfer Switch (ATS) which will deliver power to our Computer Room Air Conditioning (CRAC) units at the State Data Center. There are two (2) generators on site (one to carry the power load, with the other being a back-up just in case) which will provide power through these activities.  These activities will include migrating the CRAC units from the temporary ATS to a tertiary ATS which is now in place.   We anticipate an approximate seven hour window to accomplish this task.

AZCOOP will provide updates every 45 minutes, and there will also be a Meet Me Bridge Line established at 602-771-9093.

The next AZCOOP update will occur at the begining of these activities at 3:00 AM.

 

 