Temporay ATS Installation

Installation of the temporary ATS unit for the 2nd & 3rd floor equipment rooms started at 1030 PM. The work of switching the CRAC units on the 3rd floor to the backup generators is completed. The switch of the 2nd floor CRAC units is currently underway and progressing as expected. Currently we do not have an ETA on the completion of work.

A customer Bridge Line has been established at 866-789-8818, Passcode 574769#.

Next update will be performed at 12:30 AM.

Thank you.